When does the levy need to be paid?
A Levy Project must be lodged online with CITB and paid in full before obtaining building approval (Building Consent as granted by PlanSA or Council). If building approval / consent is not required, before the commencement of the work (including demolition).
Once a project is lodged online with CITB a Levy Notice will be emailed to the Project Owner, who will have 14 days to pay the levy amount due.
Please Note: PlanSA and CITB are separate entities. Lodging a project with PlanSA does not automatically create a Levy project with CITB. Levy projects must be lodged separately via the CITB website. The same procedure applies for any project updates, cancellations, or finalisations.
For further assistance, please contact the Levies Team at leviesteam@citb.org.au.